Decide who reserves, who issues and who closes before requisitions pile up

An IFS Cloud material requisition is the document through which material is requested for internal demand, and it runs through its own flow: request, reservation, issue and closure. If the statuses and the order of the steps are not understood, requisition lines stay partially delivered or reserved and nobody decides to close them. Stock stays reserved for internal demand that is no longer needed, and issues do not match what was requested. This article follows the 26R1 page on the material requisition.

Key takeaways

  • Material requisitions request material for internal demand, as opposed to customer orders that fulfil external demand, and they can be entered by anyone entered in the application as an Internal Customer.
  • The page lists six statuses: Planned, Released, Reserved, Partially Delivered, Closed and Stopped. A new requisition starts in Released, and the page describes no approval step.
  • The parts need to be reserved before you are allowed to issue the material.
  • A manual issue can be a lesser quantity than reserved or go line by line; a partial issue gives Partially Delivered and a full issue gives Closed.
  • A line can be closed when the remaining quantity is not needed, and deletion is only possible for lines in Planned or Released status.
  • The issue is posted with posting type M53, Issue for material requisition.

1.What is a material requisition in IFS Cloud, and who can enter one?

Material requisitions are used for requesting material for internal demands, as opposed to customer orders that fulfil external demands. A material requisition can be entered by anyone who is entered in the application as an Internal Customer, and on all the sites that are connected to the user record.

Each line has a supply code that decides how the demand is met. A line with the supply code Purchase Order results in a purchase requisition, and the supply code in the Default Material Requisition Supply field on the Inventory Part/Main tab determines the default method. Decide who may be an Internal Customer, because that setting decides who can request material.

2.Which statuses does a requisition go through?

A requisition has one of six statuses. When a material requisition is created, the order number is generated by the application, and both the header and the lines acquire the Released status. The table gives what the page says about each status.

Status What the page says
Planned If you do not want to consider the requisition as a demand, the status can be changed to Planned manually
Released Header and lines acquire it at creation; it is possible to alter the status back to Planned if necessary
Reserved Some or all the parts on the line have been reserved; the header still remains in Released status
Partially Delivered Some lines have been delivered, depending on the workflow of the material requisition
Closed The lines have been delivered and/or canceled; all lines delivered gives Closed, depending on the workflow
Stopped The order is stopped and not handled as a demand; it is not possible to reserve any lines in this status

The page describes no approval step, so this article describes none. If your process needs an approval before material is issued, settle first whether and how it can be built in your release. Workflow design is covered in the article on IFS Cloud workflows.

3.Why must parts be reserved before issue?

The page states that the parts need to be reserved before you are allowed to issue the material. Reservation is therefore the step that decides whether a line can be issued at all.

The page adds rules for reservation. Serial numbered parts should be manually reserved, and you cannot reserve a higher quantity than the quantity available in stock. The material requisition line must be reserved before a pick list can be printed. You can only un-reserve lines that have the Inventory Order supply code, and un-reserve is done by entering a negative quantity to reserve. A reservation also depends on the stock itself: the Reservation Management page states that if the inventory part is connected to a part availability control ID, the availability control shall allow reservations. The settings of that control are covered in IFS Cloud part availability control.

4.How does a manual issue work?

A manual issue can take a lesser quantity than reserved or go line by line. If all the parts have been issued, the status changes to Closed. If a partial issue is done, the status will be Partially Delivered.

An issue can also be reversed in part. The page states that this operation will not lead to any status change, and that the quantity returned cannot exceed the issued quantity. Once a line is issued, it cannot be deleted. The floor side of issuing, with scanning, is covered in warehouse data collection in IFS Cloud, and the work lists in warehouse tasks in IFS Cloud.

5.How do you close a line, and what can be deleted?

You can close a line if you decide that you do not need the remaining quantity. Closing a line is a decision for the requesting department and the warehouse together, because only they know whether the remainder is still wanted.

Deletion is narrower. Once a line is reserved, it cannot be deleted, and deletion can be done only for lines in the Planned or Released status. A line that has been reserved and is no longer needed therefore has to be handled by the reservation and closing steps and not by deleting it.

6.What does the issue book in the ledger?

The issue is posted with posting type M53, Issue for material requisition. The 26R1 page on posting control for supply chain and manufacturing lists it as M53 Issue for material requisition with Inventory, and the 25R2 page on posting types and system events lists the INTSHIP event with M53 against M1, Inventory. For consignment stock the same page lists CO-INTSHIP, which posts M53 against M60, Consignment Stock.

The requisition page has its own option for accounting data: you can make defining pre-postings a requirement when entering material requisitions. Pre-postings defined on a requisition with the supply code Purchase Order are carried over to the purchase requisition line and the purchase order line. Which accounts the postings use is a decision for finance, and how events turn into ledger entries is covered in posting control in IFS Cloud.

7.Which decisions belong to the warehouse and the requesting departments?

Three questions need an owner: who reserves, who issues and who closes. The requesting department decides what it needs and when the remaining quantity is no longer needed. The warehouse reserves and issues. Because the page describes no approval step, who may request material is controlled by the Internal Customer setting and not by a release decision. Requests that are handled outside the system, for instance in spreadsheets, are discussed in shadow spreadsheet risk in manufacturing.

8.How do you test the flow before go-live?

Test the flow with scenarios that reach each status, and write down the expected status before each one.

Scenario Expected status Owner
Create a requisition Header and lines Released Requesting department
Reserve the parts of a line Line Reserved; header remains Released Warehouse lead
Full issue Closed Warehouse lead
Partial issue Partially Delivered Warehouse lead
Close short The line is closed; record the resulting header status, which follows the workflow Requesting department
Delete a reserved line Not possible; deletion works only for Planned or Released lines Warehouse lead

9.What does a material requisition checklist contain?

The internal demand flow is ready for go-live when each of the checks below has a record behind it.

  1. The people who may request material are set up as Internal Customers.
  2. The default supply code per inventory part is decided.
  3. Someone is named to reserve, and the availability controls allow the reservation.
  4. Someone is named to issue, and to close lines with a remaining quantity.
  5. Whether pre-postings are a requirement on requisitions is decided with finance.
  6. Finance has seen the posting type M53 and its consignment variant.
  7. The six test scenarios are recorded with evidence.

10.Frequently asked questions

What is a material requisition in IFS Cloud?

A material requisition in IFS Cloud is used for requesting material for internal demands, as opposed to customer orders that fulfil external demands. It has the statuses Planned, Released, Reserved, Partially Delivered, Closed and Stopped, and a new requisition starts in Released.

Who can enter a material requisition?

A material requisition in IFS Cloud can be entered by anyone who is entered in the application as an Internal Customer. It can be entered on all the sites that are connected to the user record. The page describes no approval step.

Why do I have to reserve before I can issue?

The IFS Cloud documentation states that the parts need to be reserved before you are allowed to issue the material. Serial numbered parts should be manually reserved, and you cannot reserve a higher quantity than the quantity available in stock.

What happens to the status when I issue part of the quantity?

If a partial issue is done on a material requisition in IFS Cloud, the status will be Partially Delivered. If all the parts have been issued, the status changes to Closed. You can close a line if you decide that you do not need the remaining quantity.

When can a line of a material requisition be deleted?

Deletion of a material requisition line in IFS Cloud can be done only for lines in the Planned or Released status. Once a line is reserved, it cannot be deleted, and once a line is issued, it cannot be deleted either.

11.About the author

Dariusz Myśliwiec: 18 years hands-on with IFS, including IFS Cloud. Based in Kraków, delivering remotely across Europe and globally through an independent practice. You talk to the consultant who does the work, not a sales layer.

IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

Do internal requests sit reserved with nobody closing them?

A review of the internal demand flow with the warehouse and the requesting departments shows which lines wait for a decision nobody owns.