Describe the Level 0 and Level 1 structure before planners read the proposals

Master Production Schedule Level 1 is the level of the IFS Cloud master schedule where you plan long-term demand for parts that are manufactured or purchased. Its calculation creates supply proposals of five kinds. If nobody described which parts are Level 0 and which are Level 1, forecasts are entered at the wrong level and the proposals are read as something they are not. The planned supply for manufactured and purchased parts then follows from a structure nobody wrote down. This article follows the 26R1 page on Master Production Schedule Level 1 and two 25R2 activity pages for the calculation and the manual update.

Key takeaways

  • When Level 1 is calculated, master schedule proposals create shop order requisitions and/or production schedules and/or purchase requisitions and/or supplier schedules and/or distribution orders.
  • Level 1 parts are the leaf nodes of planning structures; with planning on an aggregated family level, the topmost part is a Level 0 part, and Level 0 forecasts are disaggregated into Level 1 forecasts.
  • A part does not need a Level 0 to be planned in MS Level 1.
  • Demand explosion to components planned by master scheduling stops when it hits an MRP planned component.
  • The page names nine parameters for the Level 1 calculation, among them Rolling, lot sizes and Rate by Period.
  • A manual update replaces the existing master production schedule receipt value and sets the status to Fixed.

1.What is Level 1 of the master schedule, and what does it plan?

At MS Level 1 you plan long-term demand for parts that are manufactured or purchased. The Calculate MS Level 1 activity requires that you have entered master schedule level 1 parts and registered forecasts, and the registration of level 1 parts can be handled manually or automatically from the level 0 calculation. The result is a gross demand, which forms the basis of MRP.

The parts processed in MS on level 1 do not generate supplies during MRP, unless specifically set to create supplies during MRP for actual demands of MS parts. How MRP then uses structures is covered in dynamic structures and MRP.

2.How do Level 0 and Level 1 parts relate in a planning structure?

Level 1 parts can be considered the end items, because they are at the leaf nodes of planning structures.

Level Position in the structure Forecasts
Level 0 The topmost part of the planning structure, when planning is performed on an aggregated family level Level 0 forecasts are disaggregated, and forecast information comes to Level 1 from Level 0
Level 1 Leaf nodes of planning structures Planned directly, or received from Level 0; a part does not need a Level 0 to be planned in MS Level 1

The time fences of Level 0 and Level 1 parts and the lead time behind them are defined on the IFS time fence page. Lead time definitions are covered in lead times in IFS Cloud and the routing calculation in routing lead time calculation. This page states one calendar rule: when master scheduling plans are supplied, the manufacturing calendar connected to the site is used for manufactured parts and the distribution calendar for purchased parts.

3.What does the calculation create?

The page names five kinds of objects that the master schedule proposals create when Level 1 is calculated.

  • Shop order requisitions
  • Production schedules
  • Purchase requisitions
  • Supplier schedules
  • Distribution orders

The calculation considers the manufactured/acquired split, the supplier split, the standard multiple quantity and the lot sizes. Fixed proposals within the planning time fence create requisitions only if the Proposal Release field on the Inventory Part/Planning Data tab is set to Release, indicating that supply for the part is not managed by Kanban circuits. For supplier schedules, the demand time fence and planning time fence on the Master Schedule Level 1 Part page should be set to 0, because supplier schedule template rules are applied.

4.What happens to dependent demand?

If component parts are planned by MS or defined as MS level 1 parts, the supply proposals for parent parts created by MS are broken down and explode demands to these MS planned components. During MS level 1 calculation, demand explosion stops when it hits an MRP planned component.

The multilevel MS Level 1 calculation will only consider consecutive MS planned parent-child relations in the product structure.

5.Which parameters shape the schedule?

The page section Important Parameters for Level 1 Calculation names nine parameters. Three of them are described below with the page’s own wording.

Parameter What the page says
Rolling In the page’s example, an excess part quantity of 100 is subtracted from the first master schedule proposal after the planning time fence
Minimum, Multiple and Maximum Lot Sizes If the minimum and maximum lot sizes are set to zero (0), the lot size is unlimited
Rate by Period The remaining quantity will be moved to the previous period, and the spread and leveling stop at the planning time fence, which is the lower boundary
Other parameters on the page Use Planned Dependent Demand; Use Dependent Demand in Forecast Consumption; Use Abnormal Demand in Forecast Consumption; Include in Import Demand Planning Forecast; Include in Import Customer Schedule; Include Purchase Order Direct Supply

The page has further sections for multi-site master scheduling, project master scheduling, supplier schedules, MTO DOP parts, consideration of shelf life expiration date in planning, integration with CRP, and starting the MRP process once MS completes. In a multi-site supply chain, it is up to you to determine manually the order in which master scheduling is executed for the sites. When MS is performed integrated with CRP, the shop order requisitions generated by MS are backward scheduled.

6.How does a planner change the Level 1 schedule by hand?

The manual update of the Level 1 master schedule requires that the master schedule calculation of level 1 has been performed. When you save the changes, the new value is evenly distributed to each workday in the period, the existing master production schedule receipt value is replaced and the status is set to Fixed. Only a fixed number of periods, the first 40, are displayed. The page gives the calculation of Available Forecast as the previous period Available Forecast value, minus Customer Forecast, minus Actual Demand, plus Work In Process, plus Level 1 Updated, and for the first period the previous period value is the quantity on hand.

7.Which messages does master scheduling raise?

The 26R1 page on master scheduling messages includes the message “Insufficient unconsumed supply to satisfy actual demand”, generated when the unconsumed supply is not sufficient to meet the actual demand. A second message, “Forecast ignored within demand time-frame”, is generated when a forecast is found inside the demand time fence, because only the actual demand is considered inside it. Promising against the master schedule is covered in Master Scheduling Available to Promise, and its relation to capable-to-promise in CTP in IFS Cloud.

8.Who owns the planning structure?

A forecast appears on a part that nobody expected to receive one, and the proposals that follow have no owner who can explain them. Each of the roles below closes that gap. The planning lead defines which parts are Level 0 and which are Level 1, because the level decides where a forecast is entered and where it is disaggregated. The planner who enters or imports forecasts knows the level of each part before the entry. The planner who reviews proposals knows which of the five object kinds each part produces and which parts stop the explosion because they are MRP planned. The business sets the meeting interval of these roles; the page gives none.

9.How do you test a Level 1 schedule before go-live?

Test with one forecast at Level 0 and one at Level 1, and write down the expected proposals before each calculation.

Scenario Expected result Owner
Forecast entered at a Level 0 part Disaggregated into Level 1 forecasts; record the quantity per Level 1 part Planner
Forecast entered at a Level 1 part with no Level 0 Planned in MS Level 1 without a Level 0 Planner
Calculate Level 1 for a manufactured part, a purchased part and a part with a supplier schedule Record which of the five object kinds each part produces Planner
Parent part with an MS planned component and a part with an MRP planned component Demand explodes to the MS planned component; explosion stops at the MRP planned component Planning lead
Maximum and minimum lot size both 0 Lot size is unlimited Planner
Manual update of one period New value distributed evenly to each workday of the period; receipt value replaced; status Fixed Planner

10.What does a master schedule set-up checklist contain?

The Level 1 set-up is ready for go-live when each check below has a record behind it.

  1. The Level 0 and Level 1 parts are listed, with the planning structure they belong to.
  2. Forecast entry and import are assigned to named planners.
  3. The MRP planned components in each structure are listed, because the explosion stops there.
  4. Rolling, lot sizes and Rate by Period are decided for each Level 1 part.
  5. Proposal Release is decided for parts whose fixed proposals must create requisitions.
  6. The reviewer of proposals and of master scheduling messages is named.
  7. The six test scenarios are recorded with evidence.

11.Frequently asked questions

What is Master Production Schedule Level 1 in IFS Cloud?

Master Production Schedule Level 1 in IFS Cloud is the level where you plan long-term demand for parts that are manufactured or purchased. When Level 1 is calculated, master schedule proposals create shop order requisitions, production schedules, purchase requisitions, supplier schedules and/or distribution orders.

What is the difference between a Level 0 and a Level 1 part?

A Level 1 part is a leaf node of a planning structure, an end item. When planning is performed on an aggregated family level, the topmost part of the planning structure is a Level 0 part, and its forecasts are disaggregated into Level 1 forecasts. A part does not need a Level 0 to be planned in MS Level 1.

What does the Level 1 calculation create?

The Level 1 calculation in IFS Cloud creates master schedule proposals that create shop order requisitions, production schedules, purchase requisitions, supplier schedules and/or distribution orders. The result is a gross demand, which forms the basis of MRP.

Where does the demand explosion stop?

During the IFS Cloud MS level 1 calculation, demand explosion stops when it hits an MRP planned component. Components planned by MS or defined as MS level 1 parts receive the exploded demands from the supply proposals of their parent parts.

How are forecasts brought into the master schedule?

The IFS Cloud Calculate MS Level 1 activity requires that you have entered master schedule level 1 parts and registered forecasts. Forecast information also comes to Level 1 from Level 0 once the Level 0 forecasts are disaggregated.

12.About the author

Dariusz Myśliwiec: 18 years hands-on with IFS, including IFS Cloud. Based in Kraków, delivering remotely across Europe and globally through an independent practice. You talk to the consultant who does the work, not a sales layer.

IFS is a registered trademark of IFS AB; this practice is not affiliated with IFS AB.

Does your master schedule produce proposals nobody knows how to read?

A review of the planning structure and the Level 1 set-up with your planners shows which parts sit at which level and what each calculation creates.

Book a master schedule review Read about Available to Promise